The company's Longjing environmental protection Shanxi Tongcai desulfurization and denitration ultra-low emission device project has successfully completed the production target

浏览 Source: Unknown Release time: 2019-06-06 09:18 Times

Recently, our company's Shanxi Tongcai Project Department came to Xircom, and with the joint efforts of the project department and all parties, it successfully completed the desulfurization and reconstruction project in the plant area, which was five days ahead of the owner's request. This is the smooth realization of another important node after the completion of the construction of the denitration device in January.

The 360㎡ sintering machine flue gas desulfurization and denitrification ultra-low emission device installation project undertaken by Fujian Longjing Desulfurization and Denitrification Engineering Company of Fujian Longjing Desulfurization and Denitrification Engineering Co., Ltd. undertaken by our company is the largest environmental protection project cooperation between the company and Fujian Longjing Desulfurization and Denitrification Company Facing many difficulties such as the large volume of non-standard production projects, the high risk of high-altitude operations, the limited construction space for the reconstruction of old factories, the heavy workload of secondary handling, and the tight schedule requirements, the general contractor has very strict requirements for the project schedule, repeatedly asking the company Make arrangements for construction deployment and ensure each construction node unconditionally. In order to ensure the realization of the contract goals, the company leaders attached great importance to the project management team, which established Comrade Liu Zhihui, who is known as a dare to fight hard, and was quickly involved in all preparations for the project construction.

Under the company's overall deployment arrangements, the company and the project department unify their thinking, clear goals, reasonable arrangements, and careful deployment. We must win this tough battle and establish the company's image to win more markets. The project department was set up and settled on site in October 2018, and adopted a series of construction measures to increase the configuration of construction machinery; increase the number of construction personnel to improve the efficiency of construction; increase the number of overtime personnel, and arrange the second handling work as much as possible at night to ensure that overtime at night effectiveness. After the severe cold in winter, overcoming difficulties, and continued high investment and high intensity construction, the construction node of the denitration device was successfully completed on January 20, 2019.

The desulfurization construction and reconstruction construction contract period is 3 months, but the owner's furnace shutdown and maintenance time is only 40 days. It is required that the desulfurization and reconstruction construction must be completed within this time and that it is in operation. If the construction period is delayed for 1 day, a fine of 100,000 yuan will be imposed, 1 day in advance. 200,000 yuan in reward. The general contractor requires our department to complete within the prescribed time limit and promises to complete the reward 200,000 yuan in advance. Due to the close connection between the reformed part of the desulfurization device and the original desulfurization device, the amount of demolition and new construction tasks is large, and the on-site construction hoisting position is narrow, the 40-day construction period is considered an unachievable goal. In such a difficult situation, the project department clenched its teeth up and down, and organized a 300t truck crane and a 130t crawler crane in a narrow operation site, including the erection of more than 120 people in 7 work teams including the riveter team and the pipeline team. Team, division of labor and cooperation, construction at all working surfaces, working overtime at the same time, not afraid of dirty, not tired, regardless of cost and cost, after close organization and construction, with the unremitting efforts of all members of the project department, finally on May 26 In the early morning, the construction node was completed and the new desulfurization facility was officially put into operation. Complete the node goal 5 days in advance to ensure the owner's production and operation.

At this point, Shanxi Tongcai Industry and Trade Co., Ltd.'s 360 square meter sintering machine flue gas desulfurization and denitration ultra-low emission device installation project has been basically completed. This is our company's wonderful appearance on environmental protection projects, which once again demonstrated the spirit of unity and hard work of Xinan people. Style, established a good corporate image of Xin'an!